The question
To ask the Scottish Government which minister (a) was responsible for producing and (b) signed-off the original contract for the construction of the Aberdeen Western Peripheral Route (AWPR).
The answer
Subject to the resolution of the legal challenges to the statutory processes for the scheme, Ministers indicated that the AWPR/B-T project would be progressed as a “non-profit distributing” (NPD) contract in the 2011 Infrastructure Investment Plan,.
Following the procurement process the contract was awarded to Aberdeen Roads Limited (ARL) in 2014 .
The contract is a standard form NPD model, developed under the governance of Scottish Futures Trust. Consequently, no further Ministerial approval of the documents was required.
Following the procurement process the contract was awarded to Aberdeen Roads Limited (ARL) in 2014 .
The contract is a standard form NPD model, developed under the governance of Scottish Futures Trust. Consequently, no further Ministerial approval of the documents was required.
In the Official Report