Further to the answer to question S5W-17470 by Humza Yousaf on 25 July 2018, by what date the findings of the  independent deliverability a…

Answered Asked by Liam Kerr Con Lodged 3 Oct 2018

The question

To ask the Scottish Government, further to the answer to question S5W-17470 by Humza Yousaf on 25 July 2018, by what date the findings of the independent deliverability assessment will be published.

The answer

Answered by Humza Yousaf on 19 Oct 2018 · 16 days after it was lodged, on time

The purpose of the replanning exercise on BTP integration was to identify when a fully integrated high quality service could be delivered. Once the replanning exercise was completed a Gateway Review was to have taken place to test the deliverability of the project.
The Scottish Government announced its decision in August to re-examine all options for the devolution of railway policing in Scotland. Therefore, a Gateway Review will not be conducted at this time.

In the Official Report

No contribution in the Official Report cites S5W-19173 by reference.