Further to the answer to question S5W-18914 by Michael Matheson on 2 October 2018, whether all of the trains will have controlled emission …

Answered Asked by Colin Smyth Lab Lodged 2 Oct 2018

The question

To ask the Scottish Government, further to the answer to question S5W-18914 by Michael Matheson on 2 October 2018, whether all of the trains will have controlled emission tanks fitted before they are used.

The answer

Answered by Michael Matheson on 25 Oct 2018 · 23 days after it was lodged, on time

Abellio ScotRail (ASR) are currently examining whether installing Controlled Emission Tanks (CET) prior to the full refurbishment of ‘Classic’ High Speed Trains (HST) is possible and they are also looking at temporary measures to mitigate the impact of operation without CET installed. Transport Scotland continues to press ASR on a resolution and that ASR continue to address any concerns that the travelling public and trades unions have around the use of ‘Classic’ HST units without CET installed.

In the Official Report