Written Question · S5W-16319 · Session 5
Further to the answer to question S5W-15962 by Keith Brown on 1 May 2018, whether it will provide the information that was requested regard…
The question
To ask the Scottish Government, further to the answer to question S5W-15962 by Keith Brown on 1 May 2018, whether it will provide the information that was requested regarding how it had planned to pay for the A90 grade separated junction at Laurencekirk, prior to the announcement of City Region Deal funding, and where any funds have been reallocated.
The answer
There was no budget allocated for the A90 grade separated junction at Laurencekirk prior to the announcement of the Aberdeen City Region Deal. The announcement in January 2016 confirmed that the £24 million was additional investment by the Scottish Government following the Deal.
In the Official Report
No contribution in the Official Report cites S5W-16319 by reference.