Written Question · S5W-15323 · Session 5

Whether it will provide an update on what the planned completion date is for the Aberdeen Western Peripheral Route (AWPR) and, if this has …

Answered Asked by Lewis Macdonald Lab Lodged 15 Mar 2018

The question

To ask the Scottish Government whether it will provide an update on what the planned completion date is for the Aberdeen Western Peripheral Route (AWPR) and, if this has changed, when it did so.

The answer

Answered by Keith Brown on 27 Mar 2018 · 12 days after it was lodged, on time

In my statement to Parliament on 22 March 2018 I advised that there is effectively a range of dates when the road is likely to be open. The earliest date is likely to be towards the end of the summer period, however it may be more prudent to anticipate a late autumn 2018 opening date for project opening.
When I attended the Rural Economy and Connectivity Committee on 24 January 2018, I advised that the intention at that time remained to open the road in the spring but that the date could not be guaranteed. Since that time, Transport Scotland has been working closely with Aberdeen Roads Limited (ARL) to work through the information available to understand the timeframes for opening the project roads
Balfour Beatty, who is one of the partners forming ARL published its 2017 full-year results on 14 March 2018. Within these results it is suggested that the project will be complete in summer 2018. Transport Scotland urgently met with ARL’s contractor on 15 March 2018 to understand its definitive position on the project opening. The information received from the contractor has been considered together with independent assessments undertaken by Transport Scotland’s technical advisors. The conclusion reached is that the earliest that all roads can realistically be open is predicted to be towards the end of the summer period with the latest in mid to late autumn 2018.
Notwithstanding this Transport Scotland is also establishing whether any further mitigation measures can be put in place to ensure the project is not only delivered at the soonest opportunity but toidentify if sections of new road can be opened in advance of the whole of the project.

In the Official Report