What its position is on whether EPC measures for the U-value of stone construction in Scotland fairly represent actual in situ performance.

Answered Asked by Graham Simpson Con Lodged 27 Nov 2017

The question

To ask the Scottish Government what its position is on whether EPC measures for the U-value of stone construction in Scotland fairly represent actual in situ performance.

The answer

Answered by Kevin Stewart on 12 Dec 2017 · 15 days after it was lodged, on time

EPCs are produced using the UK Government National Calculation Methodology (NCM) that conforms to the requirements of the Energy Performance of Buildings Directive (2010/31/EU).
Within the NCM, default U-values for the performance of building elements are provided for use in the calculation methodology where it is impractical to obtain building-specific U-values. These U-values are developed by the UK Government to be representative of typical constructions.
A recent UK Government review of the NCM resulted in changes to default values cited for solid and cavity brick construction. We are currently investigating whether a similar review of U-values for stone external wall construction is merited.

In the Official Report