The question

To ask the Scottish Government, further to the answers to questions S5W-11879 and S5W-12280 by Keith Brown on 6 October and 31 October 2017 respectively, for what reason there was a delay between the finalisation and publication of the accounts for (a) Scottish Enterprise and (b) Highlands and Islands Enterprise.

The answer

Answered by Keith Brown on 21 Dec 2017 · 28 days after it was lodged, on time

Although the annual report and accounts for Scottish Enterprise and Highlands and Islands Enterprise are signed off by their respective Accountable Officers during the summer, there are a number of internal processes that need to be followed before the accounts can be laid at Parliament.
These processes account for the time difference between the Accountable Officers signing off their accounts and the accounts being published.
The Scottish Government always ensures that the audited accounts for Scottish Enterprise and Highlands and Islands Enterprise are laid and published as early as possible and within the statutory requirements set out.

In the Official Report