Written Question · S5W-11378 · Session 5

Further to the answer to question S5W-11110 by Humza Yousaf on 14 September 2017, for what reason the delivery date has been delayed by thr…

Answered Asked by Jamie Greene Con Lodged 19 Sep 2017

The question

To ask the Scottish Government, further to the answer to question S5W-11110 by Humza Yousaf on 14 September 2017, for what reason the delivery date has been delayed by three months; what change there has been to the capital cost since the contract was signed; which Caledonian Maritime Assets Ltd terminals can currently accept the new vessels, and which will need upgraded, broken down by the cost of these improvements.

The answer

Answered by Humza Yousaf on 28 Sep 2017 · 9 days after it was lodged, on time

The decision to move the launch date was taken by the shipbuilder, Ferguson Marine Engineering Ltd (FMEL), to enable a greater quantity of internal outfitting to be completed prior to the vessel’s launch after which all further work has to be completed whilst the vessel is afloat alongside the outfitting berth.
There have been some design changes during the build process and, at this point, additional costs agreed between the contracting authority, Caledonian Maritime Assets Ltd (CMAL), and FMEL relate to enhanced mooring arrangements at £800k per vessel.
The vessel to be named the MV Glen Sannox is earmarked for the Ardrossan to Brodick route and Hull 802 is earmarked for the Uig to Lochmaddy and Tarbert (Harris) routes.
Redevelopment of the harbour and the terminal at Brodick is in the final stages of completion by CMAL. Works at Tarbert (Harris) are at the design stage and the necessary Environmental Impact Assessments and Harbour Revision Orders are being pursued. Works being undertaken at ports throughout the ferry network owned by CMAL and other authorities are planned on the basis of need which often relates to their age and volume of use. The two vessels under construction will be able to operate to the designated ports but in each case the ports are, in any event, required to undergo renewal in order to ensure the long term sustainability of the infrastructure and to maintain and enhance customer experience.
The new Brodick terminal will be within the budget of £30m and the current plans for Tarbert (Harris) indicate an estimated cost of £15m. The three other ports, Ardrossan, Uig and Lochmaddy, are not CMAL.