Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S5W-11078 · Session 5

When work on the Maybole bypass will begin; whether it will be dualled road, and what its position is on developing a cycle track alongside…

Answered Asked by Brian Whittle Con Lodged 5 Sep 2017

The question

To ask the Scottish Government when work on the Maybole bypass will begin; whether it will be dualled road, and what its position is on developing a cycle track alongside it.

The answer

Answered by Humza Yousaf on 20 Sep 2017 · 15 days after it was lodged, on time

The current programme anticipates award of the main construction contract for the A77 Maybole Bypass in autumn 2018. Ground investigation works are anticipated to start later this year. Procurement of both contracts has commenced. The bypass will not be dualled, although increased overtaking opportunities will be provided on the new road in each direction.
The 5km scheme is considered to take the heavy traffic flow out of Maybole High Street, making for a safer environment for cyclists through Maybole. A footway/cycleway will be created to divert pedestrians and cyclists from the A77 into Maybole.

In the Official Report

No contribution in the Official Report cites S5W-11078 by reference.