With regard to the Cloich Forest Wind Farm development, whether (a) a full hydrological survey has been carried out, (b) a risk assessment …
The question
To ask the Scottish Government, with regard to the Cloich Forest Wind Farm development, whether (a) a full hydrological survey has been carried out, (b) a risk assessment has been completed and (c) mitigation measures are in place.
The answer
An assessment of impacts of Cloich wind farm on hydrology and private water supplies was undertaken by the applicant. This was reported in chapter 11 of the environmental statement which accompanied the application. Ministers consulted a range of interested parties on the application, including SEPA and Scottish Water on the terms of the hydrology and private water supply assessments. Neither consultee with an interest in hydrology and water quality maintained an objection to the proposal. Scottish Ministers held an inquiry in relation to the proposed development over various dates in May and June 2015, which included examination of evidence in relation to hydrology and private water supplies, all as reported in the Scottish Ministers’ decision to grant section 36 consent and direct that planning permission be deemed to be granted on 8 July 2016.
The section 36 consent and deemed planning permission for Cloich wind farm was granted subject to a number of conditions to control construction and operation of the wind farm to control environmental effects of the development. These include express prohibitions on commencement of development until a method statement for delivery of mitigation measures on private water supplies and details of water and flood risk mitigation measures have been approved by the planning authority.
The consent for Cloich wind farm has not yet been implemented and Scottish Ministers have been informed that the Company has not yet submitted its pre-commencement method statements for approval by Scottish Borders Council.
The decision letter for Cloich can be viewed at: www.energyconsents.scot
The section 36 consent and deemed planning permission for Cloich wind farm was granted subject to a number of conditions to control construction and operation of the wind farm to control environmental effects of the development. These include express prohibitions on commencement of development until a method statement for delivery of mitigation measures on private water supplies and details of water and flood risk mitigation measures have been approved by the planning authority.
The consent for Cloich wind farm has not yet been implemented and Scottish Ministers have been informed that the Company has not yet submitted its pre-commencement method statements for approval by Scottish Borders Council.
The decision letter for Cloich can be viewed at: www.energyconsents.scot
In the Official Report