Further to the answer to question S5W-08561 by Humza Yousaf on 19 April 2017, what discussions it had with (a) Shetland Line 1984 Ltd and (…

Answered Asked by Lewis Macdonald Lab Lodged 9 May 2017

The question

To ask the Scottish Government, further to the answer to question S5W-08561 by Humza Yousaf on 19 April 2017, what discussions it had with (a) Shetland Line 1984 Ltd and (b) Streamline Shipping Group regarding pay rates on the vessel chartered to deliver the six-year public contract, and what proportion of the government grant was spent on the contractor’s charter costs.

The answer

Answered by Humza Yousaf on 24 May 2017 · 15 days after it was lodged, on time

The six-year Public Service Contract was paid to support the movement of freight to and from the Northern Isles and concluded in May 2014. The contractor’s charter costs were a matter for the commercial operator Shetland Line 1984 Ltd.

In the Official Report