What impact the fire on the Leeds-Aberdeen high-speed train (HST) on 21 March 2017 will have on the plans for HST services to be introduced…

Answered Asked by Mike Rumbles LD Lodged 22 Mar 2017

The question

To ask the Scottish Government what impact the fire on the Leeds-Aberdeen high-speed train (HST) on 21 March 2017 will have on the plans for HST services to be introduced by ScotRail from 2018.

The answer

Answered by Humza Yousaf on 18 Apr 2017 · 27 days after it was lodged, on time

The delivery of the Abellio ScotRail HST trains into service from 2018 is unaffected. The incident on an Virgin East Coast HST train on 21 March 2017 was caused by an electrical machine failure in service. The Abellio ScotRail HSTs will all be receiving an overhaul and refurbishment before entering service with Abellio ScotRail.

In the Official Report

No contribution in the Official Report cites S5W-08323 by reference.