Written Question · S5W-07976 · Session 5

When Caledonian Maritime Assets Ltd will complete the re-development of Brodick Harbour, and what the final cost will be.

Answered Asked by John Finnie Green Lodged 9 Mar 2017

The question

To ask the Scottish Government when Caledonian Maritime Assets Ltd will complete the re-development of Brodick Harbour, and what the final cost will be.

The answer

Answered by Humza Yousaf on 16 Mar 2017 · 7 days after it was lodged, on time

The Brodick ferry terminal redevelopment works are on programme and due to be substantially complete in August 2017.
The final outturn costs of the project is anticipated to be within the £30.8m project budget.