Written Question · S5W-07976 · Session 5
When Caledonian Maritime Assets Ltd will complete the re-development of Brodick Harbour, and what the final cost will be.
The question
To ask the Scottish Government when Caledonian Maritime Assets Ltd will complete the re-development of Brodick Harbour, and what the final cost will be.
The answer
The Brodick ferry terminal redevelopment works are on programme and due to be substantially complete in August 2017.
The final outturn costs of the project is anticipated to be within the £30.8m project budget.
The final outturn costs of the project is anticipated to be within the £30.8m project budget.
In the Official Report