Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S5W-07722 · Session 5

Further to the answer to question S5W-06893 by Maureeen Wattr on 24 February 2017, noting that this funding was listed in both the draft 20…

Answered Asked by Neil Findlay Lab Lodged 3 Mar 2017

The question

To ask the Scottish Government, further to the answer to question S5W-06893 by Maureeen Wattr on 24 February 2017, noting that this funding was listed in both the draft 2016-17 budget and the draft 2017-18 budget, whether the delivery of £150 million funding began in the financial year 2016-17 or will begin in 2017-18, and what the final financial year of the allocation of funds will be.

The answer

Answered by Maureen Watt on 16 Mar 2017 · 13 days after it was lodged, on time

The commitment within the Scottish budget to invest £150 million over the next five years is from 2017-18 to 2021-22. £30 million is earmarked for allocation in 2017-18. The allocation profile for future years is currently being agreed, and will be subject to future Spending Review decisions.

In the Official Report

No contribution in the Official Report cites S5W-07722 by reference.