In light of the vision set out by Scottish Water in its report, Delivery Plan 2015 to 2021, that it should be “trusted to care for the wate…

Answered Asked by John Lamont Con Lodged 16 Nov 2016

The question

To ask the Scottish Government, in light of the vision set out by Scottish Water in its report, Delivery Plan 2015 to 2021, that it should be “trusted to care for the water on which Scotland depends”, what discussions it has had with the company regarding the delay in completing the repairs to the public sewer in Hawick that was damaged by a storm in December 2015, and what its position is on the (a) delay and (b) reports that, until the work is completed, the majority of the town’s sewage will be pumped overland.

The answer

Answered by Roseanna Cunningham on 29 Nov 2016 · 13 days after it was lodged, on time

The storms of December 2015 caused significant damage to Hawick’s wastewater infrastructure. The Scottish Government was kept fully informed of the scale of the damage. It expected Scottish Water to focus on restoring services as quickly as possible and to take all necessary measures to ensure that sewage did not pollute the River Tweed. It accepts that this meant that temporary arrangements had to be put in place whilst permanent and durable repairs are undertaken.