What commitments regarding the (a) cost and (b) timetable for completing the upgrading works on the A7 were given by the Minister for Trans…

Answered Asked by Oliver Mundell Con Lodged 23 Sep 2016

The question

To ask the Scottish Government what commitments regarding the (a) cost and (b) timetable for completing the upgrading works on the A7 were given by the Minister for Transport and Islands at his meeting with the A7 Action Group in June 2016.

The answer

Answered by Humza Yousaf on 4 Oct 2016 · 11 days after it was lodged, on time

I met the A7 Action Group in Parliament on 15 June 2016 to discuss their Action Plan, which set out its aspirations for the route. I committed Transport Scotland to undertake a review of the Action Plan and engage directly with the A7 Action Group regarding this review. The review has now been completed and has identified a range of items within the Action Plan that we will consider further. This will be done alongside on-going maintenance and improvement programmes on the route. We will also continue to monitor road safety on the A7 and through this approach will identify the need for any further road safety investigations or improvements.

In the Official Report

No contribution in the Official Report cites S5W-03148 by reference.