The question

To ask the Scottish Government, further to the answer to question S5W-01610 by Kevin Stewart on 8 August 2016, whether it and the Joint Housing Policy and Delivery Group have determined the level of credit required to increase the pace and momentum of housing delivery in order to meet the 50,000 new homes target.

The answer

Answered by Kevin Stewart on 20 Sep 2016 · 15 days after it was lodged, on time

Minutes from previous meetings of the Joint Housing Policy and Delivery Group can be viewed on the Scottish Government website: http://www.gov.scot/Topics/Built-Environment/Housing/reform/jhpdg/jhpdg-meetings

In the Official Report

No contribution in the Official Report cites S5W-02330 by reference.