General Question · S5O-02508 · Session 5
What tree planting has been undertaken recently on the upgraded sections at Uddingston as part of the M8 M73 M74 Motorway Improvements Proj…
The question
To ask the Scottish Government what tree planting has been undertaken recently on the upgraded sections at Uddingston as part of the M8 M73 M74 Motorway Improvements Project.
The answer
Planting season runs from November to March, as such no planting has taken place recently. Scottish Roads Partnership, the contractor for the M8 M73 M74 Motorway Improvements Project has recommenced tree planting and landscaping works on the project now that the planting season is once again underway. The majority of landscaping works at Uddingston have been completed with the remainder programmed between November 2018 and March 2019. This includes the planting of trees, shrubs and grassland areas.
In the Official Report
No contribution in the Official Report cites S5O-02508 by reference.