In which month it anticipates the Aberdeen Western Peripheral Route will be fully open.

Answered Asked by Lewis Macdonald Lab Lodged 20 Feb 2018

The question

To ask the Scottish Government in which month it anticipates the Aberdeen Western Peripheral Route will be fully open.

The answer

Answered by Keith Brown on 1 Mar 2018

We have always been clear about the timescale for this project. I have previously stated the intention to open the AWPR this Spring and indeed, on a recent site visit, I saw for myself that work has been progressing in recent months and the new road is now clearly visible to local communities.
However, it is becoming apparent that Carillion’s announcement may have some impact on this programme indirectly through the effect on the supply chain and we are working closely with Aberdeen Roads Limited to mitigate those impacts where we can.
Clearly, on a site like this, extreme weather events such as Storm Frank in 2015 and this week’s exceptional weather conditions will have consequential impacts on progress. However, we are continuing to work with the contractor and our stakeholders, with a view to delivering the benefits associated with opening sections of the project as soon as it is safe to do so.

In the Official Report

No contribution in the Official Report cites S5O-01819 by reference.