To ask the Scottish Government whether it will provide an update on its tax incremental financing scheme.
The answer
Three tax incremental financing pilots are currently in the construction phase. They are in Argyll and Bute, Falkirk and Glasgow. A pilot for Fife has been approved in principle with the final agreement anticipated to be signed soon.
Due to changed market conditions, and with the agreement of the relevant local authorities, the pilots for Edinburgh and North Lanarkshire are not proceeding as planned. However, other options to support economic growth are being taken forward or are being considered.
Scottish Futures Trust has written to all local authorities in Scotland inviting them to submit proposals to replace the two pilots not being taken forward and will work with my officials to identify which of the proposals submitted will be taken forward as a pilot.
Due to changed market conditions, and with the agreement of the relevant local authorities, the pilots for Edinburgh and North Lanarkshire are not proceeding as planned. However, other options to support economic growth are being taken forward or are being considered.
Scottish Futures Trust has written to all local authorities in Scotland inviting them to submit proposals to replace the two pilots not being taken forward and will work with my officials to identify which of the proposals submitted will be taken forward as a pilot.