Written Question · S4W-30456 · Session 4
Further to the answer to question S4W-27757 by John Swinney on 27 October 2015, whether the contracts have been signed and, if so, whether …
The question
To ask the Scottish Government, further to the answer to question S4W-27757 by John Swinney on 27 October 2015, whether the contracts have been signed and, if so, whether it will now provide the information that was requested.
The answer
Information on when contracts have been signed is given in the following table:
Project
Planned Date
Actual Date
Ayr Academy
Q3 2015
7 January 2016
Dalbeattie Learning Campus
Q3 2015
25 January 2018
Newbattle High School
Q1 2015
12 February 2016
Kelso High School
Q2 2015
19 February 2016
Elgin High School
Q2 2015
25 February 2016
Baldragon Academy, Dundee
Q1 2015
26 February 2016
Inverclyde Care Home
Q1 2016
26 February 2016
William McIllvaney Campus, Kilmarnock
Q1 2016
24 February 2016
Planned dates reflect the agreed point where projects became impacted by classification issues.
A further four projects are scheduled to reach financial close in the coming weeks and information on those projects is given in the following table:
Current Planned
Planned Date
Actual or Current Planned Date
Barrhead High School
Q3 2015
21 March 2016
Our Lady and St Patrick's High School
Q3 2015
24 March 2016
Oban High School and Campbeltown Grammar
Q1 2016
24 March 2016
NHS Lothian Partnership Centre Bundle
Q1 2015
29 March 2016
The Scottish Government provides revenue support for these projects with a value of over £200 million. This support has been adjusted to protect local authorities and NHS boards from the inflationary pressures incurred through delays. These revenue cost pressures, actively managed by Scottish Futures Trust in collaboration with procuring local authorities and NHS boards and with the hub companies, have been offset by a reduction in the cost of finance during 2015 and early 2016 leading to a negligible budget impact across the eight projects.
Project
Planned Date
Actual Date
Ayr Academy
Q3 2015
7 January 2016
Dalbeattie Learning Campus
Q3 2015
25 January 2018
Newbattle High School
Q1 2015
12 February 2016
Kelso High School
Q2 2015
19 February 2016
Elgin High School
Q2 2015
25 February 2016
Baldragon Academy, Dundee
Q1 2015
26 February 2016
Inverclyde Care Home
Q1 2016
26 February 2016
William McIllvaney Campus, Kilmarnock
Q1 2016
24 February 2016
Planned dates reflect the agreed point where projects became impacted by classification issues.
A further four projects are scheduled to reach financial close in the coming weeks and information on those projects is given in the following table:
Current Planned
Planned Date
Actual or Current Planned Date
Barrhead High School
Q3 2015
21 March 2016
Our Lady and St Patrick's High School
Q3 2015
24 March 2016
Oban High School and Campbeltown Grammar
Q1 2016
24 March 2016
NHS Lothian Partnership Centre Bundle
Q1 2015
29 March 2016
The Scottish Government provides revenue support for these projects with a value of over £200 million. This support has been adjusted to protect local authorities and NHS boards from the inflationary pressures incurred through delays. These revenue cost pressures, actively managed by Scottish Futures Trust in collaboration with procuring local authorities and NHS boards and with the hub companies, have been offset by a reduction in the cost of finance during 2015 and early 2016 leading to a negligible budget impact across the eight projects.