Written Question · S4W-29192 · Session 4
(a) what the timescales are and (b) how many responses it has received for the tender processes for the research projects, (i) Transport Im…
The question
To ask the Scottish Government (a) what the timescales are and (b) how many responses it has received for the tender processes for the research projects, (i) Transport Impacts, (ii) Decommissioning and Aftercare and (iii) Seismic Activity and Monitoring, which are part of its consultation on unconventional oil and gas.
The answer
The three research projects are currently out to tender. Responses to the tenders are due on 22 January 2016 for the transport and decommissioning projects and 29January 2016 for the seismic activity project.
In the Official Report
No contribution in the Official Report cites S4W-29192 by reference.