On how many of the 309 weekdays between 15 December 2014 and 12 December 2015 rail services on the Far North Line achieved 100% reliability.

Answered Asked by Rhoda Grant Lab Lodged 5 Jan 2016

The question

To ask the Scottish Government on how many of the 309 weekdays between 15 December 2014 and 12 December 2015 rail services on the Far North Line achieved 100% reliability.

The answer

Answered by Derek Mackay on 20 Jan 2016 · 15 days after it was lodged, on time

Of the 309 weekdays between 15 December 2014 and 12 December 2015, 100 percent reliability (that is, no full cancellations, part-cancellations, or incidents where a train failed to stop where it should have stopped) was achieved on 216 days.

In the Official Report

No contribution in the Official Report cites S4W-29164 by reference.