How much it would cost to construct a flow-over canopy on the A83 at the Rest and be Thankful to prevent the road being closed due to lands…
The question
To ask the Scottish Government how much it would cost to construct a flow-over canopy on the A83 at the Rest and be Thankful to prevent the road being closed due to landslides, and what plans it has to (a) build such a canopy or (b) introduce other measures to permanently resolve the issue.
The answer
The A83 Trunk Road Route Study published in February 2013 considered a series of options with the objective to reduce the impact of the effects of landslides at the Rest and Be Thankful. This transport appraisal was undertaken in accordance with Scottish Transport Appraisal Guidance and Stage 1 scheme assessment in accordance with the Design Manual for Roads and Bridges.
Six options were appraised and this is fully discussed in the A83 Trunk Road Route Study, Part A which can be found on the Transport Scotland website at the following link: http://www.transportscotland.gov.uk/system/files/uploaded_content/documents/projects/A83/a83-rest-and-be-thankful-project-a83-trunk-road-route-study-report-part-a-final.pdf
The “Brown Option” considered a 1km debris flow shelter. Following the initial sift against the stated criteria, the options for a flow-over canopy was sifted out for further consideration as other options were assessed to perform better against the appraisal criteria. Also similar benefits could be achieved with other options in the study at lower cost and with a lower potential environmental impact.
The Scottish Government remains committed to working with local communities and businesses to ensure that Argyll remains open for business. This has seen an investment of over £48 million in maintaining the A83 since 2007. This includes £9 million towards reducing the risk of impacts from landslides at the Rest and Be Thankful and the establishment of the local diversion route. The A83 taskforce will reconvene on 25 January 2016, when the continued work of the group and next steps will be discussed.
Six options were appraised and this is fully discussed in the A83 Trunk Road Route Study, Part A which can be found on the Transport Scotland website at the following link: http://www.transportscotland.gov.uk/system/files/uploaded_content/documents/projects/A83/a83-rest-and-be-thankful-project-a83-trunk-road-route-study-report-part-a-final.pdf
The “Brown Option” considered a 1km debris flow shelter. Following the initial sift against the stated criteria, the options for a flow-over canopy was sifted out for further consideration as other options were assessed to perform better against the appraisal criteria. Also similar benefits could be achieved with other options in the study at lower cost and with a lower potential environmental impact.
The Scottish Government remains committed to working with local communities and businesses to ensure that Argyll remains open for business. This has seen an investment of over £48 million in maintaining the A83 since 2007. This includes £9 million towards reducing the risk of impacts from landslides at the Rest and Be Thankful and the establishment of the local diversion route. The A83 taskforce will reconvene on 25 January 2016, when the continued work of the group and next steps will be discussed.