Further to the answer to question S4W-26441 by John Swinney on 31 July 2015, whether all projects with a financial close date of after Sept…

Answered Asked by Jackie Baillie Lab Lodged 27 Sep 2015

The question

To ask the Scottish Government, further to the answer to question S4W-26441 by John Swinney on 31 July 2015, whether all projects with a financial close date of after September 2014 have been affected by the Eurostat change.

The answer

Answered by John Swinney on 27 Oct 2015 · 30 days after it was lodged, on time

Project timetables can be affected by a wide range of factors. Twelve hub projects are considered to be in a position where they would be likely to be able to move to financial close now should current classification issues be resolved. Other hub projects in the pipeline are scheduled to reach financial close later in 2015.

In the Official Report

No contribution in the Official Report cites S4W-27760 by reference.