Written Question · S4W-27567 · Session 4
When differential speed limits on the A85 will be brought into place.
The question
To ask the Scottish Government when differential speed limits on the A85 will be brought into place.
The answer
The Speed Limit Review recommended five separate reductions to speed limits on the A85. An update on each of these proposals is provided below:
Crieff to Comrie – Draft road orders were published in November 2014 and a number of objections to this proposal have been received. Transport Scotland met with the objectors on 16 June 2015 to discuss the concerns raised and we are now actively considering these representations. The timeframe for the delivery of a speed limit reduction is subject to the satisfactory conclusion of this process.
Comrie to Fillans – Draft road orders were published in September 2015 inviting comments from members of the public on this proposal. This period of consultation is ongoing and the delivery of this speed limit reduction is subject to the outcome of this process.
Lochearnheadside – Draft road orders will be published later in 2015 inviting comments from members of the public on this proposal. The delivery of this speed limit reduction is subject to the outcome of this process.
East Huntingtower to Lochty – The statutory process to promote and consult on this speed limit reduction has been completed. We have instructed our operating company to install the required signage and it is programmed that the new speed limit will come into force during October/November 2015.
Lochearnhead to Lixtoll – The statutory process to promote and consult on this speed limit reduction has been completed. We have instructed our operating company to install the required signage and it is programmed that the new speed limit will come into force before the end of November 2015.
Crieff to Comrie – Draft road orders were published in November 2014 and a number of objections to this proposal have been received. Transport Scotland met with the objectors on 16 June 2015 to discuss the concerns raised and we are now actively considering these representations. The timeframe for the delivery of a speed limit reduction is subject to the satisfactory conclusion of this process.
Comrie to Fillans – Draft road orders were published in September 2015 inviting comments from members of the public on this proposal. This period of consultation is ongoing and the delivery of this speed limit reduction is subject to the outcome of this process.
Lochearnheadside – Draft road orders will be published later in 2015 inviting comments from members of the public on this proposal. The delivery of this speed limit reduction is subject to the outcome of this process.
East Huntingtower to Lochty – The statutory process to promote and consult on this speed limit reduction has been completed. We have instructed our operating company to install the required signage and it is programmed that the new speed limit will come into force during October/November 2015.
Lochearnhead to Lixtoll – The statutory process to promote and consult on this speed limit reduction has been completed. We have instructed our operating company to install the required signage and it is programmed that the new speed limit will come into force before the end of November 2015.
In the Official Report
No contribution in the Official Report cites S4W-27567 by reference.