Further to the answer to question S4O-04551 by John Swinney on 9 September 2015 (Official Report c. 5), whether the planned timetable for t…

Answered Asked by Alison McInnes LD Lodged 10 Sep 2015

The question

To ask the Scottish Government, further to the answer to question S4O-04551 by John Swinney on 9 September 2015 (Official Report c. 5), whether the planned timetable for the Aberdeen Western Peripheral Route project now differs from the details provided in the answer to question S4W-24246 on 2 February 2015.

The answer

Answered by John Swinney on 25 Sep 2015 · 15 days after it was lodged, on time

There is no change to the delivery timetable of the Aberdeen Western Peripheral Route since the updates given in the answer to question S4W-24246 on 2 February 2015, and reconfirmed in the answer to question S4W-26951 answered on 31 July 2015, which made clear that there would be no effect on either the timetable or cost of the Aberdeen Western Peripheral Route.
All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at:
http://www.scottish.parliament.uk/parliamentarybusiness/28877.aspx.

In the Official Report

No contribution in the Official Report cites S4W-27447 by reference.