Written Question · S4W-26442 · Session 4

Which capital projects have been delayed as a result of the changes to the Eurostat designation of capital projects and what the (a) length…

Answered Asked by Jackie Baillie Lab Lodged 1 Jul 2015

The question

To ask the Scottish Government which capital projects have been delayed as a result of the changes to the Eurostat designation of capital projects and what the (a) length of delay and (b) additional cost is in each case.

The answer

Answered by John Swinney on 31 Jul 2015 · 30 days after it was lodged, on time

The eight hub design-build-finance-maintain (DBFM) projects that had been due to reach financial close by the end of 2014-15 had not reached financial close by 31 March 2015. For project specific reasons, the Forfar Academy and Anderson High School Shetland have been allowed to progress to financial close. Elgin High School, Baldragon Academy Dundee, Newbattle High School, Kelso High School, NHS Lothian Health Centre Bundle, and Inverclyde Care Home have been affected by a combination of Eurostat and other project specific programme issues. Other hub DBFM projects due to reach financial close in the early part of the current financial year, Our Lady and St Patricks High School and Barrhead High School, have faced project specific issues and are now also affected by the need for further consideration of the implications of the review by the Office of National Statistics of the classification of the Aberdeen Western Peripheral Route. The length and cost of any delay will only be known when contracts are signed.