Written Question · S4W-26160 · Session 4
Who is responsible for (a) monitoring and (b) enforcing planning conditions relating to onshore windfarm developments and hydro schemes and…
The question
To ask the Scottish Government who is responsible for (a) monitoring and (b) enforcing planning conditions relating to onshore windfarm developments and hydro schemes and whether ring-fenced funding is provided for this purpose.
The answer
Planning authorities are responsible for (a) monitoring and (b) enforcing planning conditions relating to onshore windfarms and hydro schemes. It is for the landowner, unless otherwise specified, to ensure that the conditions of consent for development on their land are accorded with.
Funding is not ring-fenced for these purposes but comes from the general local government settlement.
Funding is not ring-fenced for these purposes but comes from the general local government settlement.