Written Question · S4W-25422 · Session 4
How much double-tracking between Inverness and Nairn, as set in August 2014 in the document, Aberdeen to Inverness Rail Improvements Projec…
The question
To ask the Scottish Government how much double-tracking between Inverness and Nairn, as set in August 2014 in the document, Aberdeen to Inverness Rail Improvements Project GRIP 3 – Phase 1 Enhancements, is to be provided; where it will be laid, and what the timescale is for the work.
The answer
Infrastructure improvements for the Aberdeen to Inverness Improvements project, including some double tracking between Inverness and Nairn, will be prioritised for delivery in the next phase of the project (during Control Period 6 2019-24). I can confirm that the Scottish Government is absolutely committed to delivering significant journey time improvements and greater connectivity on the Inverness to Aberdeen corridor, including enhancing services between Inverness and Elgin.
In the Official Report
No contribution in the Official Report cites S4W-25422 by reference.