How many trains will be required to operate on the Borders railway line and how many will be (a) new, (b) taken from other ScotRail service…

Answered Asked by Tavish Scott LD Lodged 23 Feb 2015

The question

To ask the Scottish Government how many trains will be required to operate on the Borders railway line and how many will be (a) new, (b) taken from other ScotRail services, broken down by service, and (c) hired from other operators.

The answer

Answered by Derek Mackay on 6 Mar 2015 · 11 days after it was lodged, on time

The timetable for the Borders railway requires seven trains. The rolling stock will be from the train fleet Abellio ScotRail will be using to deliver the contractualised Abellio ScotRail franchise services.