Written Question · S4W-24441 · Session 4
Further to the answer to question S4W-24217 by Derek Mackay on 11 February 2015, whether it will confirm that the next Clyde and Hebrides f…
The question
To ask the Scottish Government, further to the answer to question S4W-24217 by Derek Mackay on 11 February 2015, whether it will confirm that the next Clyde and Hebrides ferry services contract will be for six years from October 2016.
The answer
Previous ferry service contracts have been set at six years. The next contract will run from 1 October 2016 up to a period of eight years to allow the operator more scope to invest in and deliver service efficiencies and improvements over a longer operating period. The contract will be subject to a mid-point review in year four, which could limit its duration to six years.
In the Official Report
No contribution in the Official Report cites S4W-24441 by reference.