Written Question · S4W-24213 · Session 4
What additional operational costs have been incurred by CalMac in the operation of the Ullapool to Stornoway ferry service that are associa…
The question
To ask the Scottish Government what additional operational costs have been incurred by CalMac in the operation of the Ullapool to Stornoway ferry service that are associated with the delay in the installation of suitable berthing facilities for the MV Loch Seaforth at Ullapool and Stornoway.
The answer
The additional operational costs incurred by CalMac Ferries Ltd associated with the delay in the installation of suitable berthing facilities for the MV Loch Seaforth at Stornoway and Ullapool relate to the extension of the charter of the MV Clipper Ranger. The vessel is expected to be required until the end of May 2015. The additional charter costs for this extension are £1.4 million.
In the Official Report
No contribution in the Official Report cites S4W-24213 by reference.