Further to the answer to question S4W-24001 by Alex Neil on 21 January 2015, whether it has made an assessment of the impact on achieving r…

Answered Asked by Michael Russell SNP Lodged 22 Jan 2015

The question

To ask the Scottish Government, further to the answer to question S4W-24001 by Alex Neil on 21 January 2015, whether it has made an assessment of the impact on achieving renewables targets if the maximum planning fee for wind farm developments is raised to the same level as applied in England, Wales and Northern Ireland.

The answer

Answered by Alex Neil on 4 Feb 2015 · 13 days after it was lodged, on time

The Scottish Government consulted on proposals to amend the planning fee structure in 2012. As part of that consultation comments were invited on a draft Business and Regulatory Impact Assessment based on the proposed changes. Responses included some concern from industry that the proposed changes could adversely affect the viability of development projects.