Written Question · S4W-24089 · Session 4

Whether it has carried out a study of the impact on the Western Isles economy of the decision to delay improvement works on Ullapool harbou…

Answered Asked by David Stewart Lab Lodged 19 Jan 2015

The question

To ask the Scottish Government whether it has carried out a study of the impact on the Western Isles economy of the decision to delay improvement works on Ullapool harbour for a five-week period from 20 April 2015 and whether it is aware that B&B owners in Lewis are receiving cancellations due to the lack of sailings during this period.

The answer

Answered by Derek Mackay on 29 Jan 2015 · 10 days after it was lodged, on time

In order to ensure the timely completion of the Stornoway-Ullapool ferry project and entry into service of the MV Loch Seaforth, I have set up a taskforce and chaired the first meeting on 15 January 2015. I will be chairing the second taskforce meeting in Stornoway on 2 February 2015.
The role of the taskforce is to identify issues and to ensure that the project is completed by the end of May 2015. Membership of the taskforce includes Comhairle nan Eilean Siar, Stornoway Port Authority, Ullapool Harbour Trust, CalMac Ferries Ltd and Caledonian Maritime Assets Ltd.
The taskforce agreed that the Ullapool linkspan replacement works should now be undertaken between 20 April 2015 and 24 May 2015. These works were originally scheduled to take place between 22 February 2015 to 7 April 2015 but have been delayed due to overruns of the pier works being undertaken by Stornoway Port Authority. Further delays to the Ullapool works would mean that the resilience and service benefits of the new facilities would take longer to be put in place, and would add to the overall cost of the improvements. A study on the impact on the Western Isles economy during the five week closure to vehicle ferry traffic has therefore not been undertaken.
VisitScotland, in conjunction with CalMac, is looking at an additional marketing investment to encourage visitors and mitigate any impact the islands may suffer from the short term disruption at Ullapool.
Provisional timetables for 20 April to 24 May have been drafted and CalMac are talking to all interested parties about the details. CalMac have posted background information and answers to “frequently asked questions” relating to the planned closure at Ullapool. The link to this information can be found at:
http://www.calmac.co.uk/ullapool-linkspan-closure.htm