Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S4W-23661 · Session 4

Further to the answer to question S4W-23410 by Fiona Hyslop on 11 December 2014, whether it will nonetheless carry out an equality impact a…

Answered Asked by John Finnie Ind Lodged 11 Dec 2014

The question

To ask the Scottish Government, further to the answer to question S4W-23410 by Fiona Hyslop on 11 December 2014, whether it will nonetheless carry out an equality impact assessment of the decision of Historic Scotland not to schedule the Tinkers’ Heart as a monument of national importance, and what the reasons are for its position on this matter.

The answer

Answered by Fiona Hyslop on 8 Jan 2015 · 28 days after it was lodged, on time

As I explained previously, equality impact assessment is applied to new or revised plans, policies and strategies, but is not normally applied to individual operational decisions, such as which monuments and structures to designate.
However, the Chief Executive of Historic Scotland has undertaken to consider this matter further and I will offer an update in due course.

In the Official Report

No contribution in the Official Report cites S4W-23661 by reference.