Written Question · S4W-23459 · Session 4
Whether it will provide an updated timescale for works on the Aberdeen Western Peripheral Route.
The question
To ask the Scottish Government whether it will provide an updated timescale for works on the Aberdeen Western Peripheral Route.
The answer
As I announced last week following the issue of the intention to award letter to Connect Roads, the project is now scheduled to be completed ahead of programme in winter 2017.
In the Official Report
No contribution in the Official Report cites S4W-23459 by reference.