The Scottish Government currently has two sites with renewable energy sources: Saughton House, Broomhouse Drive, Edinburgh (Solar Hot Water) installed 2011 and Tweedbank, Cotgreen Road, Galashiels (Solar Hot Water) installed 2012
There are three renewable projects in the pipeline for 2015:
Longman House, 28 Longman Road, Inverness (Solar PV) 2015 subject to planning,
Faskally, Pitlochry, Perthshire (Biomass Boiler) 2015 subject to planning and
Thainstone Court, Inverurie (Biomass Boiler) 2015 subject to planning.
There are three renewable projects in the pipeline for 2015:
Longman House, 28 Longman Road, Inverness (Solar PV) 2015 subject to planning,
Faskally, Pitlochry, Perthshire (Biomass Boiler) 2015 subject to planning and
Thainstone Court, Inverurie (Biomass Boiler) 2015 subject to planning.