Which hospitals have or are developing plans on how to carry out a complete evacuation, and which have decided that such a plan is not requ…

Answered Asked by John Pentland Lab Lodged 13 Nov 2014

The question

To ask the Scottish Government which hospitals have or are developing plans on how to carry out a complete evacuation, and which have decided that such a plan is not required.

The answer

Answered by Shona Robison on 26 Nov 2014 · 13 days after it was lodged, on time

All NHS boards would deal with an evacuation, as with any disruption to their activities or buildings, as part of business continuity management arrangements. Strategic business continuity management guidance has been issued to NHS boards in Scotland and is an essential activity in establishing an organisation’s resilience. Evacuation of premises and the scale of the evacuation will be based on a risk assessment of each hazard or disruption. NHS boards are also required to carry out regular training and exercising based on the hazards and risks likely to cause disruption to their services and buildings.
Along with guidance on business continuity management, guidance aimed at ensuring that adequate provision is made for the conduct of evacuations from hospital premises was issued to NHS boards in 2011.

In the Official Report

No contribution in the Official Report cites S4W-23142 by reference.