Further to the answer to question S4W-11500 by Keith Brown on 4 December 2012, whether it will provide an update on when work on Dalcross r…
The question
To ask the Scottish Government, further to the answer to question S4W-11500 by Keith Brown on 4 December 2012, whether it will provide an update on when work on Dalcross railway station at Inverness Airport will (a) start and (b) be completed.
The answer
The Aberdeen to Inverness Rail Improvements works have commenced with site and ground investigations on the infrastructure necessary to provide for a new station at Dalcross.
Network Rail, Transport Scotland, the Highlands and Islands Transport Partnership and Highland Council met in October 2014 to progress detailed planning and preparatory works for the proposed Dalcross station. This should encourage promoters to accelerate their plans for the station which requires third party funding. Accordingly, the package of works remains on schedule for completion by March 2019 as specified in the government’s High Level Output Specification, published on 21 June 2012.
Network Rail, Transport Scotland, the Highlands and Islands Transport Partnership and Highland Council met in October 2014 to progress detailed planning and preparatory works for the proposed Dalcross station. This should encourage promoters to accelerate their plans for the station which requires third party funding. Accordingly, the package of works remains on schedule for completion by March 2019 as specified in the government’s High Level Output Specification, published on 21 June 2012.
In the Official Report
No contribution in the Official Report cites S4W-22927 by reference.