Further to the answer to question S4W-11500 by Keith Brown on 4 December 2012, whether it will provide an update on when work on Dalcross r…

Answered Asked by David Stewart Lab Lodged 23 Oct 2014

The question

To ask the Scottish Government, further to the answer to question S4W-11500 by Keith Brown on 4 December 2012, whether it will provide an update on when work on Dalcross railway station at Inverness Airport will (a) start and (b) be completed.

The answer

Answered by Keith Brown on 5 Nov 2014 · 13 days after it was lodged, on time

The Aberdeen to Inverness Rail Improvements works have commenced with site and ground investigations on the infrastructure necessary to provide for a new station at Dalcross.
Network Rail, Transport Scotland, the Highlands and Islands Transport Partnership and Highland Council met in October 2014 to progress detailed planning and preparatory works for the proposed Dalcross station. This should encourage promoters to accelerate their plans for the station which requires third party funding. Accordingly, the package of works remains on schedule for completion by March 2019 as specified in the government’s High Level Output Specification, published on 21 June 2012.

In the Official Report

No contribution in the Official Report cites S4W-22927 by reference.