Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S4W-22734 · Session 4

What impact the directive (a) 2014/23/EU, (b) 2014/24/EU and (c) 2014/25/EU will have on the (i) invitation to tender for the 2016-22 Clyde…

Answered Asked by Drew Smith Lab Lodged 3 Oct 2014

The question

To ask the Scottish Government what impact the directive (a) 2014/23/EU, (b) 2014/24/EU and (c) 2014/25/EU will have on the (i) invitation to tender for the 2016-22 Clyde and Hebrides ferry services contract and (ii) length of public sector contracts in the (A) maritime and (B) rail sector.

The answer

Answered by Nicola Sturgeon on 30 Oct 2014 · 27 days after it was lodged, on time

The three new procurement directives must be transposed into Scots law by 18 April 2016. The Scottish Government expects Scottish regulations to be in place towards the end of 2015.
The preliminary arrangements for the Clyde and Hebrides ferry service are underway and it is expected that the formal procurement process will commence in early 2015 and will therefore be subject to the existing, and not the forthcoming, regulations.
The duration of public contracts is not an issue that is governed by the procurement directives. In respect of maritime contracts, guidance issued by the European Commission on Council Regulation No. 3577/92 (maritime cabotage) advises a duration of six years, which may now be extended up to 12 years where justified.