The question

To ask the Scottish Government, further to the answers to questions S4W-20838 and S4W-21231 by Keith Brown on 9 May and 2 June 2014 respectively, for what reason the additional costs of providing Argyll Ferries' service have not been paid from the reserves of the parent company, David MacBrayne Limited.

The answer

Answered by Keith Brown on 17 Jun 2014 · 14 days after it was lodged, on time

The changes made to the services provided by Argyll Ferries Ltd (AFL) have all been made under the provisions of AFL’s contract with the Scottish Ministers and are therefore eligible for increased grant funding under the terms of that contract.

In the Official Report