Further to the answer to question S4W-20524 by Keith Brown on 22 April 2014, for what reason the costs for the Argyll Ferries Ltd public se…

Answered Asked by Jamie McGrigor Con Lodged 24 Apr 2014

The question

To ask the Scottish Government, further to the answer to question S4W-20524 by Keith Brown on 22 April 2014, for what reason the costs for the Argyll Ferries Ltd public service contract have risen compared with the figures provided in response to question S4W-08559 in 2012.

The answer

Answered by Keith Brown on 9 May 2014 · 15 days after it was lodged, on time

A number of revisions have been made to the financial base case of the contract with Argyll Ferries Ltd. These changes are all in accordance with the provisions of that contract:
SPT have reduced the level of grant payable for the carriage of concessionary card holders.
Funding was provided for training to meet the requirements of the EU regulation on maritime passenger rights.
A bus replacement service has been introduced to improve the resilience of the service when it is affected by bad weather.
The MV Argyll Flyer has been made the lead vessel, again in order to improve the resilience of the service;
Passenger numbers have fallen against the forecasts underpinning Argyll Ferries’ initial basecase.
Additional services have been provided on the Saturday of the Cowal Games.