What its position is on notices received under section 36 of the Electricity Act 1989 where a similar but smaller planning application has …
The question
To ask the Scottish Government what its position is on notices received under section 36 of the Electricity Act 1989 where a similar but smaller planning application has been recently rejected by the local planning authority.
The answer
In Scotland, any application to construct or operate an onshore power generating station with a capacity of over 50 megawatts (MW) requires the consent of Scottish Ministers under section 36 of the Electricity Act 1989.
Significant onshore renewable energy proposals will require an Environmental Impact Assessment. To comply with the Electricity works (Environmental Impact Assessment) (Scotland) Regulations 2000, Scottish Ministers have to consult the local planning authority, Scottish Environmental Protection Agency, Scottish Natural Heritage and internal government consultees, together with other parties who may have an interest in the development. Should the planning authority object to the application, or otherwise at the discretion of Ministers, a public inquiry is called to consider the proposal.
Significant onshore renewable energy proposals will require an Environmental Impact Assessment. To comply with the Electricity works (Environmental Impact Assessment) (Scotland) Regulations 2000, Scottish Ministers have to consult the local planning authority, Scottish Environmental Protection Agency, Scottish Natural Heritage and internal government consultees, together with other parties who may have an interest in the development. Should the planning authority object to the application, or otherwise at the discretion of Ministers, a public inquiry is called to consider the proposal.
In the Official Report