The question

To ask the Scottish Government, further to the answer to question S4W-18760 by Keith Brown on 18 December 2013, what the timetable is to carry out the further measures referred to.

The answer

Answered by Keith Brown on 14 Jan 2014 · 26 days after it was lodged, on time

The timetable for undertaking the further measures as referenced in S4W-18760 between Glasgow and Fort William/Oban will be set in the context of overall affordability and our commitments to other proposals in the strategic transport projects review.

In the Official Report