Written Question · S4W-18001 · Session 4
What cost saving resulted from not including the Maryhill railway line in the electrification programme.
The question
To ask the Scottish Government what cost saving resulted from not including the Maryhill railway line in the electrification programme.
The answer
The estimated costs for electrification of Maryhill line was around £25 million inclusive of the necessary route clearance works (structures etc).
In the Official Report
No contribution in the Official Report cites S4W-18001 by reference.