Written Question · S4W-17994 · Session 4
For what reason the electrification of the Maryhill railway line has not been included in the Edinburgh Glasgow Improvement Programme or co…
The question
To ask the Scottish Government for what reason the electrification of the Maryhill railway line has not been included in the Edinburgh Glasgow Improvement Programme or control period (CP)5 proposals and what consequent issues it foresees for the continued operation of the line.
The answer
Electrification of the Maryhill line was proposed as part of the initial Edinburgh to Glasgow Improvement Programme (EGIP). Constraints on access to Queen Street High Level would have meant some trains being removed and Anniesland services moving to the low level with passengers on the Maryhill line changing at Anniesland for forwarding connections.
However, we listened to concerns, including those made by Patricia Ferguson, around journey time extensions and adapted our plans, giving a commitment to retain the services in Queen Street High Level.
I can also confirm that Maryhill will be electrified when we roll out the electrification of the network after EGIP, as we’ve always stated.
However, we listened to concerns, including those made by Patricia Ferguson, around journey time extensions and adapted our plans, giving a commitment to retain the services in Queen Street High Level.
I can also confirm that Maryhill will be electrified when we roll out the electrification of the network after EGIP, as we’ve always stated.
In the Official Report
No contribution in the Official Report cites S4W-17994 by reference.