Written Question · S4W-17639 · Session 4
Further to the answer to question S4W-08998 by Keith Brown on 21 August 2012 and in light of the incident on the A83 at the Rest and be Tha…
The question
To ask the Scottish Government, further to the answer to question S4W-08998 by Keith Brown on 21 August 2012 and in light of the incident on the A83 at the Rest and be Thankful on 3 October 2013, what action it is taking to prevent landslips at vulnerable areas, and what specific contingencies it will introduce at the A83 to prevent future closures of the road.
The answer
The Scottish Government fully appreciates the effect of landslips on the A83 to the communities of Argyll. However, landslips are a natural result of the topography and climate of Scotland and cannot be prevented. We can reduce the effects of landslips on the road network and significant investment has been made in the last few years.
On the A83, we have concentrated our efforts on the area of the road around the Rest and be Thankful, which has suffered most from landslips in the last few years. The section of the road between the Rest and be Thankful and Loch Fyne, on which there was a landslip on 3 October, has been identified as an area that may require further remedial work. As noted at the last A83 Taskforce meeting, studies are underway on the section of the A83 through Glen Kinglas to Cairndow. If these identify additional locations for debris netting or drainage work, these will be prioritised subject to the availability of funding. In the meantime, measures are being taken to ensure that any clear up can be as fast as possible and to ensure communications are strengthened further.
On the A83, we have concentrated our efforts on the area of the road around the Rest and be Thankful, which has suffered most from landslips in the last few years. The section of the road between the Rest and be Thankful and Loch Fyne, on which there was a landslip on 3 October, has been identified as an area that may require further remedial work. As noted at the last A83 Taskforce meeting, studies are underway on the section of the A83 through Glen Kinglas to Cairndow. If these identify additional locations for debris netting or drainage work, these will be prioritised subject to the availability of funding. In the meantime, measures are being taken to ensure that any clear up can be as fast as possible and to ensure communications are strengthened further.