Written Question · S4W-17120 · Session 4

Further to the answer to question S4W-09952 by Keith Brown on 24 October 2012 and the findings in the report of the public inquiry into the…

Answered Asked by Angus MacDonald SNP Lodged 11 Sep 2013

The question

To ask the Scottish Government, further to the answer to question S4W-09952 by Keith Brown on 24 October 2012 and the findings in the report of the public inquiry into the proposed Rosyth international container terminal, whether it will receive advice from Scottish Natural Heritage on the implications of confirming the harbour revision order.

The answer

Answered by Keith Brown on 23 Sep 2013 · 12 days after it was lodged, on time

Before taking the decision to proceed with the order, I received advice from SNH on the terrestrial elements of the project to enable an appropriate assessment to be undertaken. No works can commence until a Marine Licence has been issued and SNH will provide advice to Marine Scotland in relation to any application for a Marine Licence.

In the Official Report

No contribution in the Official Report cites S4W-17120 by reference.