Written Question · S4W-16919 · Session 4
Whether it has a process in place to ensure a binding requirement on the developers of the proposed Rosyth international container terminal…
The question
To ask the Scottish Government whether it has a process in place to ensure a binding requirement on the developers of the proposed Rosyth international container terminal to undertake any mitigation measures identified in the associated environmental impact assessment.
The answer
The harbour revision order currently before Parliament contains a Schedule relating to mitigation measures. The harbour authority must comply with the provisions of that Schedule in taking forward the project.
In the Official Report
No contribution in the Official Report cites S4W-16919 by reference.