Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S4W-16919 · Session 4

Whether it has a process in place to ensure a binding requirement on the developers of the proposed Rosyth international container terminal…

Answered Asked by Angus MacDonald SNP Lodged 31 Aug 2013

The question

To ask the Scottish Government whether it has a process in place to ensure a binding requirement on the developers of the proposed Rosyth international container terminal to undertake any mitigation measures identified in the associated environmental impact assessment.

The answer

Answered by Keith Brown on 10 Sep 2013 · 10 days after it was lodged, on time

The harbour revision order currently before Parliament contains a Schedule relating to mitigation measures. The harbour authority must comply with the provisions of that Schedule in taking forward the project.

In the Official Report

No contribution in the Official Report cites S4W-16919 by reference.